ABC DETERGENT SAN. VE TİC. A.Ş.'s earthquake-damaged production, administrative, and social facilities located in Osmaniye are being demolished in phases, relocated, and renovated, in accordance with the projected investment and production plan. The project, designed to renovate the existing production facility without interrupting production or perhaps reducing capacity, consists of four phases.
Phase 1: Sequential demolition of the earthquake-damaged structures and the commencement of construction of a new production tower (Phase Y1) in the northeastern part of the campus.
Phase 2: Relocation of the existing facilities (Phase Y1) to the newly constructed production facility.
Phase 3: Demolition of the relocated production facilities and the demolition of the old structures. Construction of new production facilities (Phase Y2) is then underway in the area created by the demolition.
Phase 4: Demolition of the existing warehouse, administrative building, and social facilities, and construction of a new administrative building and R&D building (Phase Y3).
ARCHITECTURAL DESIGN: Ayhan ABANOZCU
NAME: ABC DETERJAN SAN. VE TİC. A.Ş. Osmaniye Fabrikası
LOCATION: Osmaniye - Bahçe
TYPE: Sanayi Tesisi & İdari Bina
EMPLOYER: ABC DETERJAN SAN. VE TİC. A.Ş.
PROJECT YEAR: 2024
BUILDING AREA: 12.590,00 M2
LAND AREA: 80.058,95 M2
TEAM: Ayhan Abanozcu / Zübeyde Şimşek / Betül Yaz
STATIC: ORION Mühendislik
MECHANICAL: TA Proje
ELECTRIC: Akseki Mühendislik
INTERIOR DESIGN: ...
LANDSCAPE DESIGN: ...